40 CFR Part 62, Table 4
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
| Affected facilities | Increment 1Submit final control plan | Increment 2Award contracts | Increment 3Begin on-site construction | Increment 4Complete on-site construction | Increment 5Final compliance |
|---|---|---|---|---|---|
| Affected facilities that commenced construction, modification, or reconstruction on or before June 26, 1987 (All pollutants) | January 11, 1999 | 05/18/99 | 11/16/99 | 11/19/00 | 12/19/00 |
a Table 4 or 5 of this subpart applies to MWC units subject to the Federal plan except those with site-specific compliance schedules shown in Table 6 of this subpart.
b As an alternative to this schedule, the owner or operator may close the affected facility by December 19, 2000, complete the retrofit while the affected facility is closed, and achieve final compliance upon restarting. See §§ 62.14108(c), 62.14108(d), and 62.14109(i) of this subpart.